Bid for Demolition and Site Clearance/Basis for Payment, February 22, 2000
File — Box: 2, Folder: 1
Dates:
February 22, 2000
Detail Costing Sheet package #8, February 22, 2000
File — Box: 2, Folder: 2
Dates:
February 22, 2000
Broadway Electrical Construction Incorporated bid, February 23, 2000
File — Box: 2, Folder: 3
Dates:
February 23, 2000
The Fagan Company bid 3, 5, 6, 8, 9, February 23, 2000
File — Box: 2, Folder: 5
Dates:
February 23, 2000
Broadway Electrical Construction package 3, 9, February 23-March 29, 2000
File — Box: 2, Folder: 8
Dates:
February 23-March 29, 2000
Mark One Electric Company package 6, February 23, 2000
File — Box: 2, Folder: 9
Dates:
February 23, 2000
Midwest Mechanical Contractors bid packages 3, 4, 5, 6, 8, 9, February 23, 2000
File — Box: 2, Folder: 10
Dates:
February 23, 2000
The Fagan Company Mechanical contract bid, February 23, 2000
File — Box: 2, Folder: 13
Dates:
February 23, 2000
Outline Specifications pricing package, February 24, 2000
File — Box: 2, Folder: 15
Dates:
February 24, 2000
George J Shaw Bid Demolition Earthworks, February 25, 2000
File — Box: 2, Folder: 17
Dates:
February 25, 2000
Demolition and Site Clearance Spiritas Wrecking Company, February 25, 2000
File — Box: 2, Folder: 18
Dates:
February 25, 2000